  • Under RERA, if a builder fails to give possession as promised in the agreement, the buyer can either withdraw and claim a refund with interest, or stay in the project and get interest for every month of delay.
  • Complaints go to the state Real Estate Regulatory Authority. Compensation claims are decided by its adjudicating officer.
  • Appeals go to the state Real Estate Appellate Tribunal within 60 days, and then to the High Court.
  • Homebuyers can also go to a Consumer Commission. But the Supreme Court has said that once one route is chosen for a dispute, the buyer generally cannot switch to the other for the same dispute.

Reviewed by

  • Approved ·

    Practises banking and civil disputes

    Reviewed this guide for accuracy against the sources listed below. How we review guides →

02What the law says

Your state

General information for India. State-specific notes are listed below.

Karnataka · Karnataka RERA and appeals
Keralam (Kerala) · Keralam: K-RERA, interest and appeals
Tamil Nadu · Tamil Nadu RERA, interest and appeals

03Where you can go

04How it usually works

  1. 01

    The buyer checks the possession date in the agreement for sale and the project's RERA page.

  2. 02

    Many buyers write to the builder asking for possession, interest or a refund.

  3. 03

    If it isn't resolved, a complaint is filed online with the state RERA authority, choosing either refund with interest or interest for the delay.

  4. 04

    The authority hears both sides and passes an order. Compensation claims go to the adjudicating officer.

  5. 05

    Either side can appeal to the Appellate Tribunal. A builder who appeals must first deposit at least 30% of the penalty, or the full amount payable to the buyer, or both, as the Tribunal directs.

  6. 06

    If the builder doesn't pay, the order can be enforced through the recovery process in the Act and the state's rules.

05Time limits

06Documents to gather

  • Allotment letter and agreement for sale (and whether it was registered)
  • Payment receipts, bank statements and home loan documents
  • The project's RERA registration page, showing the declared completion date
  • Builder's emails, letters and demand notices
  • Brochures and advertisements that mention possession dates
  • A timeline of payments and promised dates

07Common questions

Section 18 provides for refund with interest, and also compensation as provided in the Act. Compensation is decided by the adjudicating officer, who looks at factors such as the loss caused and whether the default was repeated.

The rate is fixed by each state's RERA rules. It is the same rate the buyer would pay the builder for a late payment.

Both are available, but the Supreme Court has held that once a buyer elects one route for a dispute, they cannot later switch to the other for the same dispute. People often take advice on this before filing, because the choice affects later options.

Complaints can still be made, and the Supreme Court has said non-registration of a project did not take away the RERA authority's jurisdiction in the case before it. Not registering a project that should be registered is itself a violation of the Act.

08Questions to ask an advocate

If you speak to an advocate, these questions can help make the conversation useful.

09Sources

This guide is general legal information for India, not legal advice. Laws and procedures change and can differ by state. For advice on your situation, speak to a qualified advocate.

Editorial policy

Get your situation organised

Vakil helps you understand your situation and prepare before you see a lawyer.